A14 Huntingdon Viaduct Strengthening
Client
Cleveland Bridge for Costain for Highways England
Project Description
The 1975 prestressed concrete viaduct carrying the A14 over the East Coast Main Line and a minor road has suffered from weak half joints in the main cantilever/suspended span for a number of years. In 2003 temporary strengthening of the joints was installed in the form of rows of underslung steel box beams with design life of 12 years. A more long term solution was pursued in 2013 due to changes in investment plans and the steel box beams were replaced by deeper, stiffer and heavier I beams. Installation of the new beams to the low headroom soffit of the concrete structure was not practical with cranes and novel techniques using a combination of heavy duty trailers, scissors lifts and fork lift trucks was used.
Cass Hayward Role(s)
- Three dimensional modelling of strengthening steelwork for the 2002 contract and preparation of drawings for fabrication
- Temporary works design for the lifting schemes for the 2013 steelwork installation
Project Statistics
- Completed August 2013
- Value £11m
- Beams increased in depth from 750mm to 1775mm
- Lifting weights of beam assemblies 21 tonnes
Special Features
- Internal anchoring steelwork in voids of concrete box girders detailed to accommodate significant variations in site dimensions and confined space working
- Lifting over railway possession
- Use of fork lift trucks
- Use of SPMT's with mounted with scissors lifts